ELECTRICAL MATERIALS FOR CM4 MCC WORK Project Details
EDIT DETAIL

Project Information

Title: ELECTRICAL MATERIALS FOR CM4 MCC WORK
Ref No: CPAX/2026/08/39
Creator: Jumanne Macha
Client: TWIGA cement
Project Type: commercial
Location: TWIGA CEMENT WAZO

Project Details

Budget: 29,000,000.00
Start Date: 2026-07-31
Expected Completion Date: 2026-08-31
Status: completed
Created Date: 2026-07-31
Last Updated: 2026-10-02 22:55:57

Budget Tracking

Total Costs: 19,340,000.00
Remaining: 9,660,000.00
Budget Used: 66.7%
Progress:
Involved Reimbursable Cost
# Date Item Name Amount
105 Aug 2026payment of electrical equipmen19,340,000.00
Total Costs: 19,340,000.00