PITCH SPORTS LIGHTS Project Details
EDIT DETAIL

Project Information

Title: PITCH SPORTS LIGHTS
Ref No: CPAX/2026/02/24
Creator: Jumanne Macha
Client: TWIGA cement
Project Type: commercial
Location: wazo

Project Details

Budget: 67,400,000.00
Start Date: 2026-01-21
Expected Completion Date: 2026-03-24
Status: completed
Created Date: 2026-01-20
Last Updated: 2026-10-02 22:55:53

Budget Tracking

Total Costs: 32,137,500.00
Remaining: 35,262,500.00
Budget Used: 47.7%
Progress:
Involved Reimbursable Cost
# Date Item Name Amount
121 Jan 2026Material Purchases28,000.00
221 Jan 2026Material Purchases35,000.00
322 Jan 2026Food and water Expenses12,000.00
424 Jan 2026Food and water Expenses6,000.00
524 Jan 2026Labour costs460,000.00
626 Jan 2026Food and water Expenses10,000.00
728 Jan 2026work wear12,000.00
829 Jan 2026Food and water Expenses20,000.00
930 Jan 2026Material Purchases5,000.00
1030 Jan 2026Material Purchases1,000,000.00
1130 Jan 2026Material Purchases500,000.00
1231 Jan 2026Material Purchases280,000.00
1331 Jan 2026Material Purchases30,000.00
1431 Jan 2026PPE gloves40,000.00
1502 Feb 2026Material Purchases105,000.00
1603 Feb 2026Labour costs200,000.00
1703 Feb 2026Labour costs85,000.00
1803 Feb 2026protective Equipment150,000.00
1904 Feb 2026Labour costs100,000.00
2006 Feb 2026Material Purchases38,800.00
2106 Feb 2026Material Purchases195,000.00
2206 Feb 2026Material Purchases150,000.00
2307 Feb 2026PPE gloves40,000.00
2407 Feb 2026Food and water Expenses500,000.00
2507 Feb 2026work wear600,000.00
2610 Feb 2026transport allowance80,000.00
2711 Feb 2026Fuel Allowance60,000.00
2811 Feb 2026Material Purchases14,500.00
2912 Feb 2026Material Purchases510,000.00
3012 Feb 2026Labour costs447,000.00
3112 Feb 2026project facilitation15,000.00
3213 Feb 2026Material Purchases20,000.00
3314 Feb 2026Food and water Expenses20,000.00
3414 Feb 2026PPE gloves54,000.00
3514 Feb 2026Material Purchases105,000.00
3614 Feb 2026project facilitation10,000.00
3714 Feb 2026Labour costs300,000.00
3819 Feb 2026transport allowance200,000.00
3920 Feb 2026Material Purchases46,200.00
4021 Feb 2026Labour costs100,000.00
4121 Feb 2026Labour costs140,000.00
4223 Feb 2026Material Purchases30,000.00
4314 Feb 2026ANDO LED LIGHTS5,000,000.00
4419 Feb 2026ANDO LED LIGHTS2,200,000.00
4512 Feb 2026pole2,500,000.00
4619 Feb 2026pole2,400,000.00
4704 Feb 2026material expenses1,115,000.00
4806 Feb 2026Labour costs100,000.00
4909 Feb 2026Electric cable7,953,000.00
5012 Feb 2026transport allowance40,000.00
5113 Feb 2026Electric cable862,000.00
5222 Jun 2026Accesories Control Room2,864,000.00
5322 Jun 2026Mason Cost350,000.00
Total Costs: 32,137,500.00